Reorder point and safety stock: the line inventory must not cross
Too much stock ties up money; too little loses sales. Two numbers decide when to order again: the reorder point and the safety stock.
The reorder point is lead-time demand
The reorder point is the stock level at which to place an order. In its basic form it is average daily demand × lead time: selling 120 a day with a nine-day lead time means ordering when stock reaches 1,080.
That assumes demand and lead time are exactly constant. Neither is, so the variation needs a buffer, and the buffer is the safety stock.
The template computes the reorder point with one multiply node, so moving the demand slider moves it at once.
Safety stock scales with the variation
Safety stock = z × demand standard deviation × √lead time. The z sets the service level, and the square root reflects how variation grows more slowly than the horizon.
With σ = 35, lead time 9 and z = 1.65, safety stock is 1.65 × 35 × 3 = 173.25. Quadruple the lead time and √4 = 2 doubles the buffer.
The reorder point is then 1,080 + 173.25 = 1,253.25: ordering there covers an average variation without running out.
Seeing it as a drawdown
A drawdown makes the number tangible. Starting at the reorder point and falling 120 a day, 1,253 units last about 10.4 days — roughly a day and a half beyond the nine-day lead time.
That extra 1.44 days (173 ÷ 120) is exactly what the safety stock buys.
With no replenishment the line is a straight slope; in reality an order fires at the reorder point and arrives after the lead time, producing a sawtooth. The straight line still shows the slack in days.
rop = daily_demand * lead_time
ss = z * demand_sd * sqrt(lead_time)
reorder = rop + ss
# 120*9 = 1080 ; 1.65*35*3 = 173.25 ; 1253.25
Moving the two numbers
More demand raises both. A longer lead time raises the reorder point proportionally but the safety stock by its square root. A higher service level raises only the safety stock.
The table moves only z. Going from 1.28 to 2.33 raises safety stock by about 82%, which is the price of moving from 95% to 99% service.
| Service level | z | Safety stock (σ35, √9) | Reorder point | Slack in days |
|---|---|---|---|---|
| 90% | 1.28 | 134.4 | 1,214.4 | 1.12 |
| 95% | 1.65 | 173.3 | 1,253.3 | 1.44 |
| 97.5% | 1.96 | 205.8 | 1,285.8 | 1.72 |
| 99% | 2.33 | 244.7 | 1,324.7 | 2.04 |
| 99.9% | 3.09 | 324.5 | 1,404.5 | 2.70 |
Watch these in a model
The standard deviation must be daily if demand is daily. Feeding a monthly σ into a daily demand inflates safety stock badly, so unify the time unit first.
When lead time itself varies, use √(L×σ_D² + D²×σ_L²) to include both. The template covers demand variation only, so a volatile lead time needs its own calculation.
And remember holding cost: more safety stock means fewer stockouts and more carrying cost. The right service level is where the two costs together are lowest.
Questions
Are the reorder point and safety stock the same?
No. The reorder point is the stock level that triggers an order; the safety stock is the buffer inside it. Reorder point = lead-time demand + safety stock.
What service level should I use?
It depends on the cost of a stockout. Hard-to-substitute parts often justify 99% or more; substitutable consumables often settle near 90%.